PRJ: Date Pasted to Another Application in Wrong Format (99256)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q99256 SUMMARY
When you copy a date from Microsoft Project and paste it in another
application, it will be pasted with the date format that is set in the
dialog box found on the View tab. (To locate the View tab, click Options on the Tools menu.) If you have set a different date format for tables in the Table Definition dialog box, this format will be overwitten by the format specified in the Options dialog box.
MORE INFORMATION
In the Options dialog box, the Date Format field controls the way dates are displayed. However, you can also edit a table and control the
date format of the selected table. In Microsoft Project, this
table-specific setting can be ovewritten by the setting in the options
dialog box.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbinfo kbinterop kbusage KB99256 |
---|
|