Project: Delaying Resources Does Not Change Task Duration (95690)
The information in this article applies to:
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
- Microsoft Project for Windows 95 4.1
This article was previously published under Q95690 SUMMARY
In Microsoft Project for Windows and Macintosh, the duration Project
calculates for the task may not look correct. This may be the case when
multiple resources are assigned to a task and a value is added to the Delay
field for one of the resource assignments.
Modification Type: | Major | Last Reviewed: | 12/12/2003 |
---|
Keywords: | KB95690 |
---|
|