You can add more work to a task even though the "% Work Complete" field of a task is set to 100% in Project Web Access 2003 (918317)
The information in this article applies to:
- Microsoft Office Project Server 2003
- Microsoft Project Web Access
SYMPTOMSYou log on to Microsoft Office Project Server 2003 by using Microsoft Office Project Web Access 2003. You then view your task assignments in Timesheet view on the View my tasks page. You notice that you can add more work to a task even though the % Work Complete field of the task is set to 100%. CAUSEIn Project Web Access 2003, you can add more work to completed tasks as follows: - If tasks in a project are tracked by the percentage of work that is complete, you can add more work to the % Work Complete field and the Remaining Work field of a task.
- If tasks in a project are tracked by actual work done and by work remaining, you can add more work to the Actual Work field and the Remaining Work field of a task.
- If tasks in a project are tracked by hours of work per day or by hours of work per week, you can add more work to the Actual Work field and the Remaining Work field of a task.
Project Server 2003 and Project Web Access 2003 work in this manner by design. WORKAROUNDTo work around this behavior, use one of the following methods if you are owner of the timesheet. Method 1: Hide the completed taskWhen you hide a task, the task is not displayed in Timesheet view. To hide a task, follow these steps: - Click the task that you want to hide, and then click Hide.
- Click OK when you are prompted to confirm that you want to hide the task.
Note After you hide a task, the task is no longer displayed on the View my tasks page. To display the task again, the project manager must either republish or update the task. Method 2: View only current tasksTo do this, click Current Tasks on the View my tasks page.
Modification Type: | Major | Last Reviewed: | 5/30/2006 |
---|
Keywords: | kbtasks kbnewfile kbprb kbtshoot kbExpertiseInter KB918317 kbAudITPRO |
---|
|