You cannot schedule items on Saturday or on Sunday in the Task Manager tool or in the Project Manager tool in Groove (915531)
The information in this article applies to:
- Groove Workspace 2.5 Professional Edition
- Groove Workspace 2.5 Project Edition
- Groove Virtual Office 3.0 Professional Edition
- Groove Virtual Office 3.0 Project Edition
- Groove Virtual Office 3.1 Professional Edition
- Groove Virtual Office 3.1 Project Edition
SYMPTOMSYou cannot schedule items on Saturday or on Sunday in the Task Manager tool in Groove Virtual Office or in the Project Manager tool in Groove Workspace.CAUSEThis issue occurs because the Task Manager tool and the Project Manager tool do not recognize Saturday and Sunday as possible work days. There are no plans to add this functionality to these tools.WORKAROUNDTo work around this issue, use the TeamDirection Project tool. With this tool, you can schedule weekend assignments. Additionally, this tool displays more calendar views and has other, more detailed features.
Note The TeamDirection Project tool is available in Groove Virtual Office Project Edition.
Modification Type: | Major | Last Reviewed: | 4/10/2006 |
---|