A master project may take longer than expected to close in Project Professional 2003 (898448)



The information in this article applies to:

  • Microsoft Office Project Server 2003
  • Microsoft Office Project Professional 2003

SYMPTOMS

When you close a master project in Microsoft Office Project Professional 2003, the master project may take longer than expected to close.

CAUSE

This issue may occur when the following conditions are true:
  • You connect to Microsoft Project Server and open the master project with the Load summary resource assignments option enabled.
  • You use the Read-only to view option to insert the project.
  • You expand the inserted project tasks while the master project is open.

    Note This issue will occur even if you collapse all the inserted project tasks before you close the master project.

WORKAROUND

To work around this issue, click to clear the Load summary resource assignments check box in the Project Server Accounts dialog box when you connect to the Project Server account.

MORE INFORMATION

To prevent the summary resource assignment information from being loaded every time that you connect to a Project Server account, install the hotfix that is described in the following article in the Microsoft Knowledge Base:

892135 The "Load summary resource assignments" check box is selected again when you reconnect to an account in Project 2003


Modification Type:MinorLast Reviewed:7/27/2006
Keywords:kbtshoot kbsavefile kbprb KB898448 kbAudEndUser