The value of the Actual Work field for a task is 0 (zero) hours when you use the Sync to Protected Actuals feature in Project Professional 2003 (892963)
The information in this article applies to:
- Microsoft Office Project Server 2003
- Microsoft Project Web Access
- Microsoft Office Project Professional 2003
SYMPTOMSWhen you use the Sync to Protected Actuals feature in
Microsoft Office Project Professional 2003, the value of the Actual
Work field for some tasks may display as 0 (zero) hours or contain
incorrect values. CAUSEThis behavior occurs if the
following conditions are true: - No resources are assigned to the task.
- The resources that are assigned to the task have never
submitted actual hours in the Project Web Access Timesheet view.
- The Project Manager makes changes to the Actual Work field in Project Professional instead of accepting the Project
Web Access Updates that are submitted by the resource.
WORKAROUNDThe Actual Work Protected field for a task is updated in Project Professional when
the following conditions are true:
- The team member who is assigned to the task uses Microsoft
Office Project Web Access 2003 to enter the actual work that was performed on
the task.
- The Project Manager then updates the actual work into the
project plan.
When you use the Sync to Protected Actuals feature, the values
in the Actual Work Protected field are written into the Actual Work field for the corresponding task. If the Project Manager manually
enters actual work in the project plan, the value of the Actual Work field will be overwritten when the Sync to Protected Actuals
feature is used. If the value of the Actual Work Protected field is not zero or if
the field does not contain the expected value, you
must compare the work that
was entered by the resource into the Project Web
Access timesheet with the value in the Actual Work Protected field for the plan. Then use one of the following workarounds
that best fits your scenario. Workaround 1 If the value in the Project Web Access timesheet is correct but
does not match the value of the Actual Work field in Project Professional 2003, use the Sync to Protected
Actuals feature to correct the value of the Actual Work field.
To do this, follow these steps:
- Start Project Professional 2003, and then open your
project.
- On the Tools menu, point to
Tracking, and then click Sync to Protected
Actuals.
Note On the Project Server, the server administrator
must turn on managed periods. To turn on managed periods, follow these
steps:
- Log on to Project Web Access 2003 as an administrator,
and then click Admin.
- In the Actions area, click
Customize Project Web Access.
- In the Time period settings area,
click Manage Periods - Allow only Project Web Access users to update
actuals during open periods, and then click Save
Changes.
- Click Save Changes.
Workaround 2 If the value in the Actual Work field in Project Professional 2003 is correct, but it does not
match the value in the Project Web Access timesheet, turn off the
Managed
Periods
setting,
and then
republish the assignments to overwrite actuals. To
do this, follow these steps:
- Turn off the Manage Periods setting in Project Web Access
2003. To do this, follow these steps:
- Log on to Project Web Access 2003, and then click
Admin.
- In the Actions area, click
Customize Project Web Access.
- In the Time period settings area,
click Non Managed Periods - Allow Project and Project Web Access users
to update actuals, and then click Save
Changes
- Start Project Professional 2003, and then open your
project.
- On the Collaborate menu, point to
Publish, and then click Republish
Assignments.
- Turn the Manage Periods setting back on in Project Web
Access 2003. To do this:
- Log on to Project Web Access 2003, and then click
Admin.
- In the Actions area, click
Customize Project Web Access.
- In the Time period settings area,
click Managed Periods - Allow only Project Web Access users to update
actuals during open periods.
- Specify the time periods that you want, and then click
Save Changes.
Workaround 3 If none of the values
in the Actual Work Protected field in Project Professional 2003 or
none of the values
in the Project Web Access timesheet is correct, remove the resource from the
task.
Then,
reassign the resource to the task and republish the assignment. By
doing this, the value of the Actual Work field and the
Actual Work Protected field for the task is 0 (zero) hours.
You must ask the resource to reenter the correct actual work into Project
Web Access. To do this, follow these steps:
- Turn off the Manage Periods setting in Project Web Access
2003. To do this, follow these steps:
- Log on to Project Web Access 2003, and then click
Admin.
- In the Actions area, click
Customize Project Web Access.
- In the Time period settings area,
click Non Managed Periods - Allow Project and Project Web Access users
to update actuals, and then click Save Changes.
- Start Project Professional 2003, and then open your
project.
- Remove the resource from the task. To do this, follow these
steps:
- Click Task Usage on the
View menu.
- Click the task, and then click the Assign
Resources button.
- Click Remove in the Assign
Resources dialog box.
- Reassign the resource to the task. To do this, click the
task, click the resource that you want in the Assign Resources
dialog box, and then click Assign.
- Click Collaborate, select
Publish and select New and Changed
Assignments.
- Turn the Manage Periods setting back on in Project Web
Access 2003. To do this:
- Log on to Project Web Access 2003, and then click
Admin.
- In the Actions area, click
Customize Project Web Access.
- In the Time period settings area,
click Managed Periods - Allow only Project Web Access users to update
actuals during open periods.
- Specify the time periods that you want, and then click
Save Changes.
MORE INFORMATION For more information about Actual Work
Protected fields, see Project Professional 2003 Help. To do this,
click Microsoft Project Help on the Help
menu. Type actual work protected fields in the
Search for box, and then click Start
searching. In the search results, click New fields in
Project.
Modification Type: | Minor | Last Reviewed: | 5/19/2006 |
---|
Keywords: | kbnewfile kbprb kbtshoot KB892963 kbAudITPRO |
---|
|