Resource availability information for Work, Remaining Availability, and Assignment Work does not show the correct information in Project 2003 (891961)
The information in this article applies to:
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
SYMPTOMSWhen you view the resource availability fields or graph types by using the Build Team Graph or by using the Resource Usage View in Microsoft Office Project 2003, the following fields or graph types may display incorrect information: - Work
- Remaining Availability
- Assignment Work
However, if you view the resource availability information in Microsoft Project Web Access, the correct information is displayed. RESOLUTIONHow to obtain the hotfixThis issue is fixed in the Microsoft Office Project 2003 Hotfix Package that is dated January 13, 2005. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 891203 Description of the Microsoft Office Project 2003 post-Service Pack 1 hotfix package: January 13, 2005 Note After you install this hotfix, this problem does not occur in a new project. To fix the assignment data in an existing project after you install this hotfix, open the project, make a change to the assignment data, and then save the project. STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|
Keywords: | kbQFE KBHotfixServer kbProject2003PreSP2fix kbbug kbfix KB891961 kbAudITPRO kbAudEndUser |
---|
|