A negative work value is unexpectedly displayed for a task when you assign a resource to a task in Project 2003 (884058)
The information in this article applies to:
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
SYMPTOMSWhen you assign a resource to a task in your project in Microsoft Office Project 2003, you experience the following symptoms when you view the task in Gantt Chart view: - A negative work value is unexpectedly displayed for the task.
- The end date of the task is incorrect.
CAUSEThis problem occurs if the task occurs on a day or at a time that is not within the availability dates and times that are specified for the resource.RESOLUTIONHow to obtain the hotfixThis issue is fixed in the Microsoft Office Project 2003 post-Service Pack 1 Hotfix Package that is dated August 30, 2004. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 883954 Description of the Project 2003 post-Service Pack 1 hotfix package: August 30, 2004 STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|
Keywords: | kbQFE KBHotfixServer kbnewfile kbProject2003PreSP2fix kbbug kbfix KB884058 kbAudITPRO |
---|
|