Microsoft Project 2002 sets the duration of a task to zero when you assign a resource that has no availability to a task (883524)
The information in this article applies to:
- Microsoft Project Standard 2002
- Microsoft Project Professional 2002
SYMPTOMSWhen you assign a resource that has no availability to a task that has fixed work or that has fixed units and that has a predefined work value, Microsoft Project 2002 sets the duration of the task to zero (0). The assignment units are set to an illogical value, such as 1000 percent or 2,000,000 percent.STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|
Keywords: | kbQFE KBHotfixServer kbbug kbfix KB883524 kbAudITPRO |
---|
|