Actual Work Protected values for assignments that are in a Resource view may be blank or display a zero for their values in Project Professional 2003 (883505)
The information in this article applies to:
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
SYMPTOMSIf you open a project file in Microsoft Office Project
Professional 2003 and then switch to an existing Resource view, any
Actual Work Protected values for assignments that are in the Resource view may be blank or
display a zero for their values. RESOLUTIONHow to obtain the hotfixThis issue is fixed in the Microsoft Office Project
2003 Hotfix Package that is dated August 25, 2004. For more information, click the following article number to view the article in the Microsoft Knowledge Base: 841361 Description of the Microsoft Office Project 2003 post-Service Pack 1 hotfix package: August 25, 2004 Note After you
install this update, you must open each project file
that experienced this problem, make a minor change
to that file, and then save
and publish the
file. This updates the file, and it resets all the
views that
are in the file. STATUSMicrosoft
has confirmed that this is a problem in the Microsoft products that are listed
in the "Applies to" section.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|