Actual Work Protected values for assignments that are in a Resource view may be blank or display a zero for their values in Project Professional 2003 (883505)



The information in this article applies to:

  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2003

SYMPTOMS

If you open a project file in Microsoft Office Project Professional 2003 and then switch to an existing Resource view, any Actual Work Protected values for assignments that are in the Resource view may be blank or display a zero for their values.

RESOLUTION

How to obtain the hotfix

This issue is fixed in the Microsoft Office Project 2003 Hotfix Package that is dated August 25, 2004. For more information, click the following article number to view the article in the Microsoft Knowledge Base:

841361 Description of the Microsoft Office Project 2003 post-Service Pack 1 hotfix package: August 25, 2004


Note After you install this update, you must open each project file that experienced this problem, make a minor change to that file, and then save and publish the file. This updates the file, and it resets all the views that are in the file.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.

Modification Type:MajorLast Reviewed:4/7/2006
Keywords:kbQFE KBHotfixServer kbtshoot kbbug kbfix KB883505 kbAudITPRO