PRJ: Tasks Missing When Printing Monthly Calendar (88787)
The information in this article applies to:
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
This article was previously published under Q88787 SUMMARY
Specifying Manual Dates when printing a Monthly Calendar with tasks showing
may cause the calendar to print with no tasks or with some tasks missing.
NOTE: The tasks that are missing do not include possible overflow tasks,
which are printed on a separate page.
REFERENCESMicrosoft Project 3.0
For more information on Monthly Calendar Reports, see pages 385-388 of the
"Microsoft Project User's Reference." For more information on printing
particular pages, see pages 353-354 of the "Microsoft Project User's
Reference."
Microsoft Project 4.0
For more information on Calendar Views, see pages 121-122 of the
"Microsoft Project User's Guide."
Microsoft Project for Windows 95 Version 4.1
For more information on Calendar Views, see pages 93-95 of the "User's
Guide for Microsoft Project for Windows 95."
| Modification Type: | Major | Last Reviewed: | 11/25/2003 |
|---|
| Keywords: | kbprb kbprint KB88787 |
|---|
|