PRJ: How Elapsed Duration Tasks Affect Slack Calculations (87301)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q87301 SUMMARY
Tasks with elapsed durations, rather than working durations, may introduce
slack into a project because these tasks can extend into nonworking
portions of the project calendar.