The percentage complete always equals zero for administrative tasks when you create an administrative project in Project Professional 2003 (867835)
The information in this article applies to:
- Microsoft Office Project Professional 2003
SYMPTOMSWhen you create an administrative project in Microsoft Office Project Professional 2003, the percentage complete always equals zero for administrative tasks.CAUSEThis problem occurs because administrative tasks in Project Professional 2003 are not intended to have a specific start and end date. Instead, administrative tasks are categories of non-working time, such as vacation or sick leave. Because administrative tasks do not have a predefined schedule, the percentage complete column for an administrative task always equals zero.
Modification Type: | Minor | Last Reviewed: | 7/27/2006 |
---|
Keywords: | kbprb KB867835 kbAudEndUser |
---|
|