Cost field values may be incorrect when you use the Analyze Timescaled Data Wizard in Microsoft Project 2002 (843609)
The information in this article applies to:
- Microsoft Project Professional 2002
- Microsoft Project Standard 2002
SYMPTOMSWhen you export data from Microsoft Project 2002 by using the Analyze Timescaled Data Wizard, the Baseline Cost value may appear incorrect on the Microsoft Excel worksheet.CAUSEThis problem may occur if there is a rounding error in the Analyze Timescaled Data Wizard.RESOLUTIONHow to obtain the hotfixThis issue is fixed in the Microsoft Project 2003 post-Service Pack 1 Hotfix Package that is dated June 25, 2004. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 870761 Description of the Microsoft Project 2002 post-Service Pack 1 hotfix package: June 25, 2004 STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|
Keywords: | kbQFE KBHotfixServer kbProject2002presp2fix kbfix kbbug KB843609 kbAudITPRO kbAudEndUser |
---|
|