Actual Work submitted by a resource in Project Web Access appears incorrect after you synchronize in Project 2003 (838009)
The information in this article applies to:
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
SYMPTOMSWhen a project manager selects Sync to Protected
Actuals after a resource has pressed DELETE or BACKSPACE to remove
Actual Work from their timesheet in Microsoft Project Web Access (PWA), the
deleted actuals may be added back into the project plan during
synchronization.RESOLUTIONThis problem was first fixed in a hotfix that is now contained in a service pack. If you installed the latest Microsoft Office 2003 service pack, you do not have to install the hotfix. Service pack informationThis problem is corrected in Microsoft Office 2003 Service Pack 1. To resolve this problem, obtain the latest service pack for Microsoft Office 2003. For additional information, click the following article number to view the article in the Microsoft Knowledge Base: 870924 How to obtain the latest service pack for Office 2003 Hotfix informationHow to obtain the hotfixThis issue is fixed in the Microsoft Office Project 2003 Hotfix
Package that is dated March 15, 2004. For additional information, click the
following article number to view the article in the Microsoft Knowledge Base: 838026 Microsoft Project 2003 hotfix package: March 15, 2004 STATUSMicrosoft
has confirmed that this is a problem in the Microsoft products that are listed
in the "Applies to" section. This problem was first corrected in Office 2003 Service Pack 1.
Modification Type: | Major | Last Reviewed: | 4/7/2006 |
---|
Keywords: | kbQFE KBHotfixServer kbProject2003sp1fix kbOffice2003sp1fix kbOffice2003preSP1fix kbfix kbbug KB838009 kbAudITPRO kbAudEndUser |
---|
|