"You do not have any scheduled work during this week" message when you use the Project Web Access Add-in for Outlook to report the hours that you worked on a task in Project Server 2003 (832595)
The information in this article applies to:
- Microsoft Office Project Server 2003
- Microsoft Project Web Access
SYMPTOMSIn Microsoft Office Project Server 2003, if you install the
Microsoft Office Project Web Access Add-in for Outlook and you use Microsoft
Outlook to report the hours that you worked on tasks that are assigned to you,
you may receive the following message:You do not have
any scheduled work during this week; To override choose "View Options" and
set the "Units" to days then enter your hours on a daily basis.You do
not have an option to configure the view options when you use Outlook with the
Project Add-in for Outlook. You have to use the View my tasks page in Microsoft
Project Web Access to configure the view options and to report the hours that
you worked per day instead of per week.CAUSEThis behavior occurs if both of the following conditions are
true:
- In Project Web Access, on the Tracking settings page, the
Time period settings setting is configured to use the
Resource should report their total hours worked for a week
option.
- You report hours that you worked on tasks in a week where
the work is not scheduled.
RESOLUTIONTo work around this behavior, use one of the following
methods:
- Set the Time period settings setting on
the Tracking settings page of Project Web Access to use the Resources
should report their hours worked every day option, and then use
Outlook with the Project Add-in for Outlook to report the hours that you
worked.
- To report the hours that you worked on tasks in weeks where
work is scheduled, use Outlook with the Project Add-in for Outlook. To report
the hours that you worked on tasks in weeks where work is not scheduled, use
the View my tasks page in Project Web Access.
MORE INFORMATIONThe "locked-down actuals" functionality that was first
introduced in Project Server 2003 improves the accuracy of how actuals are
reported and updated. Without the "locked-down actuals" functionality, when you
have to report the hours that you worked on a weekly basis, the work is
distributed across the whole week, regardless of how the work is scheduled or
when the work starts. The following is an example of a situation that
may occur without the "locked-down actuals" functionality. In this example, a
team member who is named Aaron Lee is assigned a task that is scheduled from
Wednesday, September 10 to Thursday, September 18. Aaron Lee sees this task in
his timesheet and reports the hours that he worked on this task in his
timesheet. He reports 24 hours of work because he only worked Wednesday,
Thursday, and Friday of that week. The project manager approves the work that
Aaron Lee reported, and the project manager updates the
project. However, in Microsoft Project, the updates are not applied to
Wednesday, Thursday, and Friday of that week. The updates are distributed
across the whole week, and may look similar to the following: Sun (Sept 7) Mon (Sept 8) Tue (Sept 9) Wed (Sept 10) Thur(Sept 11) Fri (Sept 12) Sat (Sept 13)
----------------------------------------------------------------------------------------------------------
Task 3.43 3.43 3.43 3.43 3.43 3.43 3.43
Aaron Lee 3.43 3.43 3.43 3.43 3.43 3.43 3.43 Project Web Access distributes and stores the information across
the whole week (including weekends) because Project Web Access cannot determine
when the work is scheduled. Although a task is actually scheduled to start on
Wednesday, September 10, the task appears with an earlier start date of Sunday,
September 7. Additionally, if other tasks depend on this task, the other tasks
are also scheduled to start earlier than their actual start dates.
This behavior may also cause other changes, including unexpected
changes in the schedule and changes in the start dates of other tasks in the
timesheet. For example, although the task is scheduled to finish on Friday,
September 18 of the following week, the work is again distributed across the
whole week. The task may appear to finish early in one week and may appear to
finish late in another week. With the "locked-down actuals"
functionality in Project Server 2003, the way that work is distributed across
weeks is improved as follows:
- If you report the hours that you worked on a task in a week
where the work is scheduled, the work is distributed based on the days that the
task is scheduled. In the example that is discussed earlier in this article,
the 24 hours of work that Aaron Lee reports is updated in Project on the days
that Aaron Lee worked. That is, the 24 hours are applied to Wednesday,
Thursday, and Friday of that week, as expected.
- If you report the hours that you worked on a task in a week
there the work is not scheduled, Project Web Access displays the message that
is described earlier in the "Symptoms" section of this article to prompt you to
change the time interval for reporting from weekly to daily. By doing so, you
can specify exactly when you did the work.
Note When you modify the view options to report the hours that you
worked on a task on a daily basis, you also see the work that you previously
reported on the day that is defined in the Time Period
settings setting as the first day of the week. You can redistribute
this work across the days of the week if you manually modify the work that is
allocated to each day. When you do so, make sure that you reduce the work that
is allocated to the first day of the week to avoid including that work two
times.
For more information about Project 2003, visit the following
Microsoft Web site:
Modification Type: | Minor | Last Reviewed: | 1/7/2006 |
---|
Keywords: | kbtasks kbReport kbprb KB832595 kbAudITPRO |
---|
|