SYMPTOMSIn Microsoft Project 2000, if you turn on the Expand
timephased data in the database option, save your project file, and
then view the project, the values TD_Value1 through TD_Value7 in the
MSP_Timephased_Data table do not match the values that are in the Task Usage
view.CAUSE This
behavior is by design.MORE INFORMATIONMicrosoft Project does not base timephased data values on
the project calendar or on the resource calendar. Microsoft Project uses a
24-hour calendar to create the timephased data values, and bases the first
TD_Value on the start date of the task. Microsoft Project calculates the other
TD_Value dates by using the TD_Units.