PRJ: Cumulative Work and Cost Extend to 12/31/2049 (77506)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
This article was previously published under Q77506 SUMMARY
The Cumulative Work and Cumulative Cost timescale calculations will extend past the end of the project end date to 12/31/49. This is designed to show you the cumulative work or costs of more than one
resource that doesn't end its work at the exact same time. Because a project finish date may not always stay static, it is necessary to extend the timescale past the project finish. If a resource is being shared from a resource pool, not all the projects may have the same finish date.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbinfo kbusage KB77506 |
---|
|