Incorrect Calculation of Earned Values for Summary Tasks (75051)
The information in this article applies to:
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q75051 SUMMARY
Microsoft Project does not correctly calculate either the
Budgeted Cost of Work Performed (BCWS) or Budgeted Cost of Work
Scheduled (BCWP) values for Summary tasks.
WORKAROUND
One way to work around this limitation is to export the earned
value information from the non-summary tasks to another application,
such as Excel, and perform the summarization there.
If you are using Microsoft Project version 4.0, you can create a Visual
Applications Edition macro that will rollup the BCWP and BCWS values from
the sub-tasks to the summary level.
STATUS
Microsoft has confirmed this to be a problem in the products listed at the
beginning of this article. We are researching this problem and will post
additional information here in the Microsoft Knowledge Base as it becomes
available. This is not a problem in Microsoft Project version 3.0.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbprb kbusage KB75051 |
---|
|