PRJ: How to Display Critical and Noncritical Milestones (65295)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
This article was previously published under Q65295 SUMMARY
A method of differentiating between critical and noncritical milestones is often desired. The Gantt Chart can be easily formatted to display a different color or shape to indicate the type of the milestone.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbhowto kbusage KB65295 |
---|
|