PRJ: How to Set up a Negative Slack Filter in MS Project (63477)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q63477 SUMMARY
When the total slack is negative, the task duration is too long for its
successor to begin on the date required by a constraint.