OL2002: The Task Reminde Displays the Reminder Time and Date Instead of the Task Due Date (292890)



The information in this article applies to:

  • Microsoft Outlook 2002

This article was previously published under Q292890
This article discusses a Beta test product that is not yet announced or released publicly by Microsoft. Please feel free to familiarize yourself with this product, test it, and report problems to Microsoft.

SYMPTOMS

When you receive a reminder for a Task item, the Due in field in the Reminders dialog box displays when the reminder for the task is due, not when the task is due.

WORKAROUND

To work around this problem, open the task item from the Reminders dialog box to see the task due date.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

Modification Type:MinorLast Reviewed:7/27/2006
Keywords:kbbug kbpending KB292890