PRJ2000: GanttChartWizard Displays High, Medium, Low for Priority Instead of 0 to 1,000 (260489)



The information in this article applies to:

  • Microsoft Project 2000

This article was previously published under Q260489

SYMPTOMS

In Microsoft Project, when you use the GanttChartWizard and you choose to display the task Priority field, the sample bars in the GanttChartWizard dialog box display priorities of High, Medium, and Low, instead of the expected values of 0 to 1,000.

WORKAROUND

Complete the GanttChartWizard. High, Medium, and Low are only examples of the text that is shown in the finished Gantt Chart view. The contents of the Priority field, which contains a value between 0 and 1,000, are actually displayed next to the bars in the formatted view.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB260489