PRJ2000: Percent Complete or Duration Change When You Change Task Type (245944)
The information in this article applies to:
This article was previously published under Q245944 SYMPTOMS
In Microsoft Project, when you change the Task type setting for a task, the task's % Complete, Actual Work, Remaining Work, and Duration fields may change as follows:
Original New Duration % Complete Actual Work Remaining Work
task type task type change change change change
--------------------------------------------------------------------------
Fixed Fixed Work, None Increase Increase Decrease
Duration Fixed Units
Fixed Work, Fixed Increase Decrease None None
Fixed Units Duration
CAUSE
This behavior may occur when the following conditions are true: - You change the Task type setting for a task as follows:
- from Fixed Duration, to Fixed Work or Fixed Units
-or-
- from Fixed Work or Fixed Units, to Fixed Duration
- The task % Complete field is greater than zero.
- The task Actual Work field is greater than zero.
- A resource is assigned to the task.
WORKAROUND
To work around this behavior, do not change the task type for a task while the task percentage complete is greater than zero.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB245944 |
---|
|