PRJ: Task Progress Bar Does Not Show Progress as Expected (245924)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q245924 SYMPTOMS
In Microsoft Project, in a Gantt Chart view, task progress bars may not be drawn to show as much progress as expected.
For example, a task progress bar may imply a task is 10 percent complete when the % Complete field indicates that it is really 50 percent complete.
CAUSE
This problem may occur when the following conditions are true:
- Your project is scheduled from the finish.
- The affected task is a predecessor of another task.
- The successor of the affected task had a percent complete value before you increased the percent complete for the affected task.
- The affected task has a percent complete value greater than zero and less than 100.
WORKAROUND
To work around this problem, follow these steps:
- In the Gantt Chart view, click Bar Styles on the Format menu.
- Select the Progress bar style.
- Click Cut Row.
- Click Paste Row.
- Click Paste Row a second time.
- For the second progress bar, in the To column, change Complete Through to % Complete.
If the Gantt Chart view has multiple progress bars, repeat steps 2-5 for each progress bar. If you don't want the additional progress bars to appear in the legend, delete the name in the Name column.
- Click OK.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB245924 |
---|
|