PRJ: Error When Changing a Resource's Working Time (234424)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q234424 SYMPTOMS
In Microsoft Project, when you change a resource's working time, the changes may not be retained or you may receive the following error message:
The Command is not available in this situation.
A command in a macro may not be available for this particular view or for the item selected.
CAUSE
The behavior occurs when you change a resource's working time and a drawing object is active on a Gantt Chart view.
WORKAROUND
To work around this behavior, select a task row before you change the resource's working time. This makes the drawing object no longer active.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB234424 |
---|
|