PRJ: Task Created in Outlook Not Recognized as Project Task (216773)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Outlook 97
- Microsoft Outlook 98
This article was previously published under Q216773 SYMPTOMS
In Microsoft Outlook, when you create new tasks in your task list, they will not be recognized as Microsoft Project tasks and will not be included in TeamUpdate or TeamStatus messages.
CAUSE
There is no way to indicate that tasks created in Microsoft Outlook are also Microsoft Project tasks. When you add a new task to your Outlook task list, it is not recognized as a Microsoft Project task because Microsoft Project tasks include addressing information that Outlook needs to populate the custom form and update tasks in Microsoft Project. If the task is created in Outlook, this information will not be available to the custom form.
WORKAROUND
To add new tasks to the list of Microsoft Project tasks assigned to a resource, the project manager has to create a task, assign the resource to the task and then send a TeamAssign message to the resource.