Content Deployment Project Does Not Run Manually When Scheduled (216178)
The information in this article applies to:
- Microsoft Site Server 3.0
This article was previously published under Q216178 SYMPTOMS
A Site Server Content Deployment project that contains spaces in the name does not run manually when scheduled.
CAUSE
This problem occurs because the scheduler application does not automatically enclose the name of the project in quotation marks.
WORKAROUND
Use one of the following workarounds:
If you must run a replication on a schedule, do not use spaces in the project name.
-OR-
In the Scheduled Tasks application, edit the task so that the project name is enclosed in quotation marks (for example:
"C:\Microsoft Site Server\Bin\Crs.exe" startrep "test replication").
-OR-
Create a publishing project name with underscores instead of spaces.
Modification Type: | Major | Last Reviewed: | 10/22/2002 |
---|