PRJ98: Unexpected Task Split in Project Created in Project 4.x (202133)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q202133 SYMPTOMS
In Microsoft Project 98, if you open a project that was created in an earlier version of Microsoft Project, a task may display any of the following behavior:
- A task with a split in its work may appear as if it does not have a split.
- A task may have less work than expected, based on how the Gantt bar is displayed.
- If you decrease or increase the duration of the task, the split where no work is assigned is replaced with work.
- If you enter percent complete on the task, a split will appear in the Gantt bar.
- If you assign an additional resource to the task, a split will appear on the Gantt bar.
CAUSE
This behavior may occur when the following conditions are true:
- You open a project created in an earlier version of Microsoft Project.
- The project contains a task where there is delay on a resource
assignment.
- The task is zero percent complete.
WORKAROUND
After you enter a percent complete on the task, Microsoft Project will display a split in the Gantt bar.
If you change the duration of the task and duration changes to an incorrect amount, follow these steps to correct it. - Re-enter the correct duration.
- On the Edit menu, click Split Task.
- In the Gantt Chart view, click the Gantt bar where you want the split to begin.
- Drag the split part to provide the split you want.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB202133 |
---|
|