PRJ98: Some Values Not Displayed at End of Timephased View (194968)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q194968 SYMPTOMS
In Microsoft Project 98, in the Task Usage, Resource Usage, and Resource
Graph view, timephased values may not be displayed correctly at the end of
the timescale.
CAUSE
This behavior may occur when a task finishes at or near the end of the
timescale.
NOTE: The timescale ends on December 31, 2049.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
| Modification Type: | Major | Last Reviewed: | 10/17/2002 |
|---|