PRJ98: Incorrect Constraint Set When Entering Timephased Work (194967)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q194967 SYMPTOMS
In Microsoft Project 98, when you enter work in the Timescale portion of a
usage view, an incorrect Start No Earlier Than constraint may be set on the
task.
CAUSE
This problem may occur when the option Tasks will always honor their constraint dates is not selected, and you manually enter work for a task or assignment in the Timescale portion of a usage view, such as the Task Usage or Resource Usage view.
WORKAROUNDWorking Around This Problem
To remove the incorrect constraint from the task, follow these steps:
- Select the task with the incorrect constraint.
- On the Project menu click Task Information and click
the Advanced tab.
- On the Constraint Task Type click As Soon As Possible
and click Ok.
Preventing This Problem
To prevent this problem from occurring, follow these steps:
- On the Tools menu, click Options and then click the
Schedule tab.
- Click to select the Tasks will always honor their
constraint dates check box and then click OK.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB194967 |
---|
|