PRJ98: Resource Not Selected for Leveling May Level Unexpectedly (193868)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q193868 SYMPTOMS
In Microsoft Project 98, when you level resources, resources not selected
for leveling or resources with the Can Level field set to No may still be
leveled for some tasks.
CAUSE
This behavior may occur in Microsoft Project 98 for any task that has
actual work and also meets all of the following conditions:
- The task has a percent complete between 0 and 100 percent.
- The task has multiple resources assigned.
- At least one of the resources assigned to the task is eligible for
leveling (has been selected for leveling, has not completed all
assigned work, and has its Can Level field set to Yes).
This behavior occurs regardless of the setting in the resources' Can Level field and regardless of whether you selected them for leveling. It also occurs whether or not Leveling can adjust individual assignments on a task is selected (to set this option, click Resource Leveling on the Tools menu).
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.