PRJ98: Cannot Edit Summary Task Fixed Cost for Inserted Project (193160)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q193160 SYMPTOMS
In Microsoft Project 98, in a consolidated project, you cannot edit the
Fixed Cost field for an inserted project's summary task.
CAUSE
The Fixed Cost field for an inserted project's summary task is a non-
editable field and is linked one-way: from the source project to the
inserted project's summary task.
WORKAROUND
To work around this behavior, change the inserted project's Fixed Cost
directly in the inserted project's source file. To do this, follow these
steps:
- On the File menu, click Open, and open the project that
is source of the inserted project in the consolidated file.
- On the Tools menu, click Options. Then, click the
View tab.
- Click to select the Project Summary Task check box. Click
OK.
NOTE: The first row in the project is the Project Summary
Task. - On the View menu, point to Table, and then click
Cost.
You can now change the Fixed Cost for this project. This change will be
reflected in the inserted project summary task in the consolidated project.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|