PRJ98: Incorrectly Distributed Timephased Baseline Cost or Work (192388)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q192388 SYMPTOMS
In Microsoft Project 98, when you view baseline information in the Task
Usage view or Resource Usage view, timephased baseline work and costs may
not be distributed over periods of working time outside of 8 A.M. to 5 P.M.
CAUSE
This behavior occurs when all of the following conditions are true:
- You create a project in Microsoft Project 4.0 where the project
calendar's working hours are partially outside the time range of 8:00
A.M. to 5:00 P.M. (for example, 4:00 A.M. to 12:00 P.M.).
- You save the project's baseline in the Microsoft Project 4.0.
- You open the project in Microsoft Project 98.
WORKAROUND
To correct this problem, edit the timephased Baseline Cost and Baseline
Work values in the Task Usage or Resource Usage views to reflect the
distribution that you want.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB192388 |
---|
|