PRJ98: Analyze_Timescaled_Data Macro Produces Incorrect Values (192026)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q192026 SYMPTOMS
In Microsoft Project 98, when you use the Analyze_Timescaled_Data macro to
export data to Microsoft Excel, you may see any of the following symptoms
when you view the data in Microsoft Excel:
Symptom 1: Cost or Work Values Are Greater Than Expected
Cost or work values for a task, resource or assignment may be greater than
expected.
For example, a resource with 8h work and $1/hr cost will have the following
values in Microsoft Excel:
Work 800.000,00h
Cost $800.000,00
Symptom 2: Costs Are Displayed in Scientific Notation
Costs are displayed in scientific notation (for example, 1E+07.00000) and
are not included in totals.
Symptom 3: Costs Are Rounded to an Incorrect Value
Most commonly, only decimal values of costs are rounded to an incorrect
value.
Symptom 4: Start and Finish times are not exported
Only start and finish dates are exported; start and finish times are not
exported.
CAUSE
These behaviors may occur when you run the Analyze_Timescaled_Data macro
that ships with Microsoft Project 98 and any of the following conditions
are true.
Condition for Symptom 1: Cost or Work Values Are Greater Than Expected
Cost or work values for a task, resource or assignment may be greater than
expected when the Digit Group Symbol is a period (.) and the Decimal Symbol
is a comma (,) under Regional Settings in Control Panel.
Condition for Symptom 2: Costs Are Displayed in Scientific Notation
Cost values greater than or equal to 9,999,999.50 in any of the following
fields may be displayed in scientific notation (for example, 1E+07.00000)
and are not included in Totals:
- Actual Cost
- Baseline Cost
- Cumulative Cost
- Fixed Cost
- ACWP
- BCWP
- BCWS
- CV
- SV
Condition for Symptom 3: Costs Are Rounded to an Incorrect Value
Values greater than or equal to $999,999.00 in the following fields may be
rounded to an incorrect value:
- Actual Cost
- Baseline Cost
- Cumulative Cost
- Fixed Cost
- ACWP
- BCWP
- BCWS
- CV
- SV
Condition for symptom 4: Start and Finish Times Are Not Exported
Start and finish values are rounded to the nearest whole day.
RESOLUTION
To correct symptoms 1-3, follow these steps:
- Obtain and install Microsoft Project 98 for Windows, Service Release
1 (SR-1). See the "Status" section later in this article for
information about obtaining and installing SR-1.
- Start Microsoft Project 98 SR-1.
- On the File menu, click Open.
- Find and open the Backup.mpt file.
NOTE: This file is found in the same directory where Winproj.exe
is located. The default location is:
C:\Program Files\Microsoft Office\Office.
- In the Organizer dialog box, click the Modules
tab.
- Under the BACKUP.MPT column, click
Analyze_Timescaled_Data.
- Click Copy. Click Yes when prompted to replace the
existing Module Analyze_Timescaled_Data
NOTE: The arrows should be pointing from the BACKUP.MPT column to
the GLOBAL.MPT column. - Click Close.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article. This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
NOTE: See the "Workaround" section of this article for additional steps after obtaining SR-1.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kbconversion KB192026 |
---|
|