PRJ98: Milestone Tasks Missing in Calendar View (191404)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q191404 SYMPTOMS
In Microsoft Project 98, some milestone tasks may not be displayed in
Calendar view.
NOTE: The milestone tasks will appear when the you print or print preview the Calendar view.
CAUSE
This problem occurs when a milestone task is scheduled to start and finish
at 12:00 A.M. (midnight).
WORKAROUND
Although you can not display milestone bars or lines in the Calendar view for milestone tasks scheduled at midnight, you can format the bar style, line color, and text color so that the text information appears in the Calendar view.
By default, milestone tasks are formatted as a solid black bar with white
text. Since the background color of the Calendar view is white, one way to work around the problem is to format the bar as a line instead, and change the text from white to black. To do this, follow these steps:
- On the Format menu, click Text Styles.
- In the Item To Change list, click Milestone
Tasks.
- Change the Color from White to Black. Click
OK.
- On the Format menu, click Bar Styles.
- In the name column, click Milestone.
- In the appearance column, click Line. Click OK.
NOTE: In step 6, you can change the bar color to white so that milestones that do not start at 12:00 A.M. display identically to tasks that do start at 12:00 A.M.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB191404 |
---|
|