PRJ: Task Changes to Milestone After Edit Assignment in Form (190613)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q190613 SYMPTOMS
In Microsoft Project, when you edit a resource assignment in the Task
Form or Task Details Form, the task may change to a milestone. Duration and
Work for the milestone will also be zero.
CAUSE
This problem may occur when you follow these steps:
- Change a resource assignment's Start and Finish dates
in the Task Form or Task Details Form to be later than
the scheduled start and finish for the task.
- Mark the task as 100% complete.
- Click OK in the Task Form.
WORKAROUND
To work around this problem, follow these steps:
- Change assignment dates in the Task Form or Task
Details and click OK.
- Mark the task as 100% complete in the Task Form or Task
Details and click OK.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB190613 |
---|
|