PRJ98: Timephased Percent Complete Recalculated When Entered (188799)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q188799 SYMPTOMS
In Microsoft Project 98, when you edit the timephased percent complete for
a task in the Task Usage view, you may see a different value than you
entered for the task.
CAUSE
This behavior is more likely to occur when the following conditions are
true:
- The task duration is a large value, for example, a year or
longer.
- The timescale shows only months, quarters, or years.
- The timephased work contour has been manually edited.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article. This problem was corrected in Microsoft Project 98 for Windows, ServiceRelease 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
MORE INFORMATION
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB188799 |
---|
|