PRJ98: Incorrect Task Duration When Opening MPX File in Project (187489)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
This article was previously published under Q187489 SYMPTOMS
In Microsoft Project 4.0, 4.1, and 4.1a, when you open an MPX 4.0 file that was saved in Microsoft Project 98, the Duration field may contain an incorrect duration. The duration is not the expected value given the start and finish dates for that task.
CAUSE
This behavior occurs when all of the following conditions are true:
- The MPX file was created in Microsoft Project 98.
- You are opening the MPX file in Microsoft Project 4.0 or 4.1.
- You have assigned a resource to a task.
- In the Task Usage view, you do any of the following:
Select a work contour other than Flat for a resource assignment.
Create a custom contour by changing the work assignment hours in the
timescale.
Enter actual work in the timescale that created a custom
contour.
WORKAROUND
To work around this problem, follow these steps when you open the project
in Microsoft Project 4.0, 4.1, or 4.1a:
- On the Tools menu, click Options and then click the
Schedule tab.
- Click to clear the Updating Task Status Updates Resource
Status check box. Click OK.
- Select all tasks in the project.
- On the Insert menu, click Task Information and then
click the Resource tab.
- In the Duration Type list, click Fixed Duration. Click
OK.
- On the Insert menu, click Task Information, then the
Resource tab.
- In the Duration Type list, click Resource
Driven.
- On the Tools menu, click Options and then click the
Schedule tab.
- Click to select the Updating Task Status Updates Resource
Status check box. Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbbug kbnofix KB187489 |
---|
|