PRJ98: Can't Resolve Overallocation If Leveling Minute-By-Minute (187372)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q187372 SYMPTOMS
In Microsoft Project 98, when you level resources, some resource
overallocations might not be resolved, nor do you receive any messages.
NOTE: If you do receive leveling messages, there may be other causes such as task constraints, task Actual Start dates, or task relationships that prevent the tasks from being leveled correctly.
CAUSE
This behavior may occur when leveling is set look for overallocations on a
minute-by-minute basis.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB187372 |
---|
|