PRJ98: Cannot Change Actual Work Value When a Task Is Complete (186075)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q186075 SYMPTOMS
In Microsoft Project 98, when you type a new value in a task's Actual Work
field, the value might not change when you press ENTER.
CAUSE
This behavior occurs when a task is 100 percent complete, and the Updating task status updates resource status check box is cleared. (On the Tools menu, click Options, and then click the Calculation tab).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB186075 |
---|
|