PRJ98: Incorrect Timephased Baseline Cost in Usage View (185293)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q185293 SYMPTOMS
In Microsoft Project 98, task and assignment baseline cost may be incorrect
in the Task Usage or Resource Usage view.
CAUSE
This behavior may occur when you save a baseline and the following
conditions are true:
- A task contains a split.
- A resource assigned to the split task has multiple rates on its cost
rate tables.
WORKAROUND
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB185293 |
---|
|