PRJ98: Cannot Resolve Overallocation Error Message When Leveling (185286)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q185286 SYMPTOMS
In Microsoft Project 98, when you level a project, you may receive the
following error message:
Microsoft Project cannot resolve the overallocation of "<resource name>" on <date>.
To continue leveling other overallocated resources, click Skip.
To continue leveling and skip overallocations that cannot be resolved, click Skip All.
To stop the current leveling operation, click Stop. To remove the effects of leveling you can perform a Clear Leveling operation from the Resource Leveling dialog.
NOTE: In addition to this error, you may receive unexpected splits in one or more tasks.
CAUSE
This behavior occurs when you level a project with an overallocated
resource, and that resource is assigned nonworking time on the Project
Start Date.
WORKAROUND
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kberrmsg KB185286 |
---|
|