PRJ98: Cannot Resolve Overallocation Error Message When Leveling (185286)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q185286

SYMPTOMS

In Microsoft Project 98, when you level a project, you may receive the following error message:
Microsoft Project cannot resolve the overallocation of "<resource name>" on <date>.

To continue leveling other overallocated resources, click Skip.

To continue leveling and skip overallocations that cannot be resolved, click Skip All.

To stop the current leveling operation, click Stop. To remove the effects of leveling you can perform a Clear Leveling operation from the Resource Leveling dialog.
NOTE: In addition to this error, you may receive unexpected splits in one or more tasks.

CAUSE

This behavior occurs when you level a project with an overallocated resource, and that resource is assigned nonworking time on the Project Start Date.

WORKAROUND

To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1


Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug kberrmsg KB185286