PRJ98: How to Filter to Show Tasks That Are Behind Schedule (181116)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q181116 SUMMARY
This article describes how to create a filter that displays tasks that are
behind schedule for a specific date. It also describes how to apply a
filter using a macro.
For example, if you have a 10-day task that should have started two days
ago, the task should be 20 percent complete. If it is less than 20 percent
complete, the filter will show it. If it is 20 percent complete or more,
the filter will not show it.