PRJ98: Additional Tasks, Links, Assignments When Pasting Tasks (180923)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q180923 SYMPTOMS
In Microsoft Project 98, when you copy and paste a selection of tasks, you
may see any of the following symptoms:
- Additional tasks
- Additional or incorrect task links
- Invalid inserted projects
- Additional or incorrect resource assignments
CAUSE
This problem occurs when you copy tasks that include an inserted project
that is expanded.
In addition to pasting the inserted project as a whole, Microsoft Project
also pastes the tasks from the inserted project as individual tasks in the
consolidated project.
WORKAROUND
To work around this problem, collapse the inserted project before copying
it. To do this, click the minus sign next to the inserted project's summary
task. After you paste the selection of tasks, you can expand the inserted
project if necessary.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1