PRJ: Changing Percent Complete Causes Delay or Schedule Error (179781)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q179781

SYMPTOMS

In Microsoft Project, when you change the percent complete of a task, you may see an unexpected delay between the task and its successor, or you may receive the following error message:
You moved task <x> of '<project name>' to finish <date>. This is after the project finish date (<project finish date>).
<X> is the task number of the successor of the task you just changed, <project name> is the name of the project, <date> is the date the successor is moved to because of the delay, and <project finish date> is the project's finish date.

CAUSE

This behavior occurs when all of the following conditions are true:
  • The project is scheduled to start from finish.
  • The option "Tasks will always honor their constraint dates" is turned off.
  • The predecessor task has either a Finish No Earlier Than, or Must Finish On constraint.
  • The predecessor task finishes before its constraint date.

WORKAROUND

Change the constraint date of the predecessor task to reflect the date that the task finishes on.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbpending KB179781