PRJ: Missing Information in Details of Usage Views (179780)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q179780 SYMPTOMS
In Microsoft Project, when you open a project that contains an inserted
project, you may see that the details in the timescale of either the
Resource Usage view or the Task Usage view displays incorrect values or is
missing information.
CAUSE
This behavior occurs when you open a project that contains an inserted
project, and the inserted project's tasks are hidden.
Details of Cost, Work, and Earned Value type fields for the inserted
project are not saved in the consolidated file. When you open the
consolidated file, the inserted project is not expanded, and the details
from the inserted project are neither displayed nor included in any
calculations for summary tasks that contain the inserted project.
WORKAROUND
To show the details information for the inserted project in the Task or
Resource Usage view, expand the inserted project. On the Project menu, point to Outline, and then click Show All Subtasks.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB179780 |
---|
|