PRJ: Detail Header Missing in Task or Resource Usage View (178703)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q178703

SYMPTOMS

In Microsoft Project, when you use a Task or Resource Usage view, the Details column in the Timescale portion of the view may not show.

CAUSE

In the Task Usage or Resource Usage view, if the view is split and a view with a timescale is in the window opposite the usage view, the Detail Header will not show. The Split window can be added and removed by clicking the Window menu and then clicking Split to split the window or Remove Split to remove the split window.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbpending KB178703