PRJ: Detail Header Missing in Task or Resource Usage View (178703)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q178703 SYMPTOMS
In Microsoft Project, when you use a Task or Resource Usage view, the
Details column in the Timescale portion of the view may not show.
CAUSE
In the Task Usage or Resource Usage view, if the view is split and a view
with a timescale is in the window opposite the usage view, the Detail
Header will not show. The Split window can be added and removed by clicking
the Window menu and then clicking Split to split the window or Remove Split
to remove the split window.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending KB178703 |
---|
|