PRJ98:Baseline Cost and Timescaled BCWS Appear as Negative Value (178695)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q178695 SYMPTOMS
In Microsoft Project 98, negative Baseline Cost and BCWS values appear,
even though there are no negative costs on tasks in the project.
CAUSE
The negative costs appear when you assign a zero unit or zero work resource
to a task and the cost accrual setting for the resource is at the End.
WORKAROUND
To workaround this problem, for resources that are assigned to tasks at
zero units or zero work, change the cost accrual from End to either Start
or Prorated. To do so, follow these steps:
- On the View menu, click Resource Sheet.
- Click the resource you want to change.
- On the Project menu, click Resource Information.
- Click the Costs tab.
- Change the Cost accrual to either Start or
Prorated.
- Click OK.
- Select the affected tasks (the ones with the erroneous negative
costs).
NOTE: If a task has progress applied, you will need to first
remove the progress before performing step 8. This is done by changing
the task's % Complete to zero. - On the Tools menu, click Tracking. Click Save
Baseline and click the Selected Tasks button. Click
OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB178695 |
---|
|