PRJ98: Resource Time-Phased SV Does Not Equal Resource Total SV (178678)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q178678 SYMPTOMS
In Microsoft Project 98, in the Resource Usage view, you may see that a
resource time-phased Schedule Variance (SV) does not equal the total SV
values for the resource.
CAUSE
This behavior occurs when the following conditions are true:
- The resource was assigned to more than one task.
- A cost is assigned to the resource.
- At least one task that the resource was assigned to was
deleted.
Resource time-phased SV values are using the rolled up assignments Budgeted
Cost of Work Scheduled (BCWS) values instead of the resources BCWS values.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1